Double Bridges Farm

Relocation of sheep, beef cattle, and swine facilities from South Milledge Avenue to property in Oglethorpe County.

Type: 
Academics & Research
Phase: 
Completed/Warranty
Status: 
Inactive
Construction Dates
Construction Start Date: 
04/15/2009
Construction Completion Date: 
03/15/2011
Project Manager: 
Derek Schuber
Contractor: 
Kevin Price General Contractors / Dominy Construction
Architect: 
Koons Environmental Design / O'Brien & Gere
Project Budget: 
$5,000,000